Project C9.2019 Abstract:
The Vermont Agency of Transportation (VTrans) currently uses a lower acceptance limit on 28-day concrete compressive strength (CCS) of 4,000 psi for acceptance of in-place concrete in its construction projects. Over time, to mitigate risk, the concrete industryās response has led to increasingly higher average 28-day CCS, which is believed to be associated with increased brittleness and excessive early cracking. UVM researchers worked with VTransā Materials Testing & Certification Lab to develop a set of initial pay factors for a new double-bounded system with an upper limit as well. The scenario-based heuristic approach balances Agency risk with industry risk in the use of payment incentives and disincentives. Several likely scenarios for an initial industry response to new pay factors were simulated. The success of that research effort, and ensuing meetings with leading industry representatives, led VTrans to the decision to implement this double-bounded approach, tentatively beginning in the Spring of 2020. Pay factors are typically enforced for payment using the percent-within-limits (PWL) approach, but a drawback of the traditional PWL approach is its implicit assumption that the distribution of CCS is Gaussian so that z-scores can be used for assessment of payment, and that payment for strengths exceeding the target mean equal those falling short of the target mean by the same amount. Although this approach works well when a single lower acceptance boundary exists, it will not be likely to work when an upper and lower acceptance boundary are used, since pay factors are not likely to be identical above and below the target value. Additionally, our research teamās review of the literature and historical data in Vermont suggests that the distribution of resulting industry-wide CCS is not likely to be best-fit to a Gaussian probability distribution function (PDF) once the double-bounded system is implemented. The goal of this project is to develop a new method of enforcing pay factors for payment of in-place CCS that does not rely on the Gaussian distribution and allows for the use of an asymmetrical set of pay factors.
Principal Investigator:
James Sullivan
Institution:
University of Vermont
Co-PIs:
Dr. David Novak
Dr. Eric Hernandez
Project Type:
Competitive-Funded Research
Start Date:
4/1/2020
Project Cost:
$166,568
Project Status:
In Progress
End Date:
3/31/2022
Agency ID:
69A3551847101
Sponsors:
University Transportation Centers Program, Department of Transportation
Vermont Agency of Transportation
University of Vermont
Implementation of Research Outcomes:
This project is in its initial research phase. Implementation of Research outcomes will be reported upon completion of initial research.
Impacts and Benefits of Implementation:
This project is in its initial research phase. Impacts and benefits of the research will be reported after the implementation phase.
Related Links:
Coming Soon
Downloadable Documents
Printable Project Information Sheet
December 2020 Quarterly Progress Report
March 2021 Quarterly Progress Report
June 2021 Quarterly Progress Report
September 2021 Quarterly Progress Report
December 2021 Quarterly Progress Report
Printable Final Report